Previous reports
EstLink 2 (updated 20.12.2011)
Asset concerned, place: EstLink 2 between Finland and Estonia
Type if asset: HVDC interconnection, subsea cable
Effect on interconnector capacity (between control/bidding areas): capacity will increase by 650 MW to both directions
Project status: In manufacturing, construction and installation phase
Estimated time of completion: early 2014.
Fenno-Skan 2 (updated 20.12.2011)
Asset concerned, place: Fenno-Skan 2 between Finland and Sweden
Type if asset: HVDC interconnection, subsea cable
Effect on interconnector capacity (between control/bidding areas): capacity will increase by 800 MW to both directions
Project status: the project completed (submarine cable and converter stations)
Estimated time of completion: subsea cable project is completed and the capacity is available to the electricity market.
EstLink 2 (updated 28.12.2010)
Asset concerned, place: EstLink 2 between Finland and Estonia
Type if asset: HVDC interconnection, subsea cable
Effect on interconnector capacity (between control/bidding areas): capacity will increase by 650 MW to both directions
Project status: contracts, concerning the delivery of the cable and the construction of converter substations, have been signed
Estimated time of completion: early 2014.
Fenno-Skan 2 (updated 13.5.2008)
Asset concerned, place: Fenno-Skan 2 between Finland and Sweden
Type if asset: HVDC interconnection, subsea cable
Effect on interconnector capacity (between control/bidding areas): capacity will increase by 800 MW to both directions
Project status:contract agreements ready (submarine cable and converter stations)
Estimated time of completion: at the end of 2011.
EstLink 2 (updated 20.5.2010)
Asset concerned, place: EstLink 2 between Finland and Estonia
Type if asset: HVDC interconnection, subsea cable
Effect on interconnector capacity (between control/bidding areas): capacity will increase by 650 MW to both directions
Project status: investment decision done
Estimated time of completion: in the beginning of 2014.
Fenno-Skan 2 (updated 21.2.2008)
Asset concerned, place: Fenno-Skan 2 between Finland and Sweden
Type if asset: HVDC interconnection, subsea cable
Effect on interconnector capacity (between control/bidding areas): capacity will increase by 800 MW to both directions
Project status:negotiations with manufactures continue
Estimated time of completion: November 30, 2011
EstLink 2 (updated 17.2.2010)
Asset concerned, place: EstLink 2 between Finland and Estonia
Type if asset: HVDC interconnection, subsea cable
Effect on interconnector capacity (between control/bidding areas): capacity will increase by 650 MW to both directions
Project status: preliminary agreement signed, no investment decision done
Estimated time of completion: at the end of 2013.