Two-year period 7/2015 - 6/2017

Peak load capacity

The Energy Authority has confirmed the power plants selected for the peak load capacity arrangement for the period of 1 July 2015 to 30 June 2017.

The total volume of the capacity is 299 megawatts (MW).

Power plants for the period 1.7.2015 - 30.6.2017

Power plant unit​Maximum power, MWFuelCompany​
​Naistenlahti 1 ​129 ​natural gas ​Tampereen Energiantuotanto Oy, as of 1.1.2016 Tampereen Sähkölaitos Oy
Haapavesi​ ​160 ​heavy fuel oil ​Kanteleen Voima Oy

 

Demand response for periods 1.12.2015 - 28.2.2016 and 1.12.2016 - 28.2.2017
 
​Consumption unitMaximum power, MW​Company
Suomenoja heat pump 10​ ​Fortum Power and Heat Oy