Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ;
6.2.2002 17:00
Press Releases

Fingrid renewing the transmission connection

Fingrid Oyj, which is responsible for the main electricity transmission grid in Finland, is renewing the electricity transmission connection from Keminmaa to Röyttä in Tornio. The extension of AvestaPolarit Oy's steel mill causes a modification need on the 110 kilovolt (kV) transmission line running between Kyläjoki and Röyttä. The foundation work on the line started this week.One of the two transmission lines between Kyläjoki and Röyttä will be modernised. A new line will be built on the right-of-way which became available after the Alaraumo-Röyttä line was dismantled, and the line section running north of this will be dismantled.

The transmission line will be built on the expropriated right-of-way. Once the work is complete, there will be an expropriation procedure in which the right of use required by the transmission line is revised to correspond to the new situation.

The foundation work at the site started this week. The objective is to have the foundations ready before the ground frost period finishes. The transmission line towers will be erected in March-April and the conductors will be installed in April. Since the connection of conductors causes momentary loud sounds of explosion, the connection work will primarily be carried out between the hours of 9 in the morning and 4 in the afternoon. Potential additional earth connections will be made in the autumn after the harvesting season.

The construction work has been scheduled for the ground frost period so that it would cause a minimum of inconvenience to farming. According to the plans, the transmission line will be ready in May. Landowners have been separately informed of the starting of the building work and of the schedule of the project.

Additional information:
Antti Linna, Project Manager, + 358 30 395 5168 or + 358 40 522 7124