Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ;
12.3.2021 14:41
Projects, Current News

The modernisation of transmission lines in North Karelia is progressing

Fingrid Oyj, the transmission system operator, is modernising the old 110 kV electricity transmission network and substations in North Karelia. The work will significantly improve transmission reliability in the region.

The project involves the modernisation of approximately 112 kilometres of 110 kV power lines. In addition, two substations will be modernised, and one new substation will be built. The Kontiolahti–Uimaharja section of the transmission line will be completed in the first week of March.

Network reinforcement demands close cooperation

The improvements to the North Karelian electricity network are being planned and implemented in close cooperation with the electricity distribution system operator in the region. The work is demanding, and it requires good planning. The project will result in a more reliable electricity transmission network for the region, and transmission reliability will remain strong long into the future.

Tens of thousands of people live in the areas around the electricity networks where work is underway, and efforts are being made to minimise visible disruption. Fingrid is working on contracts with the local distribution system operators and the Fingrid customers connected to the main grid.

Contracts due for completion in 2022

Three construction projects are underway to modernise the transmission lines in North Karelia over the period between 2019 and 2022. The first contract covered the modernisation of the transmission line between Uimaharju and Pamilo. The modernisation was completed in October 2019. The transmission line between Kontiolahti and Uimaharju was upgraded next. The modernised transmission line was commissioned at the start of March 2021. The coronavirus affected the contractors’ material deliveries, and it was not possible to commission the transmission line at the end of 2020 as originally planned. The section of the transmission line between Uimaharju and Palojärvi is now under construction for completion in summer 2022.

The upgrade works at the substations in Uimaharju and Kontiolahti have been completed. An entirely new substation is under construction in Palojärvi. Work is now underway, and the new substation will be commissioned in summer 2022.

TMV Line Oy is the contractor for all the transmission line contracts. Caverion Suomi Oy is the contractor for the Uimaharju substation, and TMV Service Oy is the contractor for the Kontiolahti and Palojärvi substations. Overall, the network reinforcements in North Karelia will cost Fingrid approximately EUR 30 million.

Additional information:

Antti Linna, Project Manager
tel. +358 30 395 5168